Analisis Penerapan Manajemen Waktu Pekerjaan Instalasi Listrik PT. Duta Bangun Sentosa dengan Metode Critical Path Method (CPM) pada Proyek Lampung City

  • Muhammad Jihaddien Daffa Universitas Singaperbangsa Karawang
  • Sukanta Sukanta Universitas Singaperbangsa Karawang

Abstract

Project implementation often occurs delays from the initial plan when the project plan is completed due to several factors. This problem also occurs in the construction of an apartment building and a mall which is being implemented by PT. Duta Bangun Sentosa which went slower than planned. To return the project's progress to the original plan, an effort to accelerate the duration of the project using the Critical Path Methode, this method is needed to find out the optimal critical path, time, and cost in the Lampung City Apartment Bay semi-basement project. This research uses direct observation to the project site to obtain data on work duration and costs. The results of the critical path in the Bay Mall and Lampung City Apartment semibasement project obtained the critical path for work A(1)→B(1)→C(2)→F(5)→I(5)→L(5)→ P(5)→Q(1)→R(1) with a total of 26 weeks of work at a cost of Rp. 3,732,000,000 (three billion seven hundred and thirty-two million rupiah). This result is an acceleration of the project from the initial plan of 32 weeks. Although it costs quite a lot, this project can reduce the duration of work to achieve the project target

References

Abdurrasyid Abdurrasyid, Luqman Luqman, Abdul Haris, Indrianto Indrianto. (2015). Implementasi Metode PERT dan CPM pada Sistem Informasi Manajemen Proyek Pembangunan Kapal.

Amri Gunasti, A. R. (2019). Penerapan Metode Barchart, CPM, PERT dan Crashing Project dalam Penjadwalan Proyek Pembangunan Gedung G Universitas Muhammadiyah Jembe. REKAYASA JURNAL TEKNIK SIPIL.

Andi Hari Maret, T. H. (2014). Analisis Proyek Pemeliharaan Irigasi Sungai Pemali Di CV. Wigati Dengan Metode CPM-PERT Menggunakan Software Ms. Project.

Ardabil Maulana, F. K. (2019). Time Optimization Using CPM, PERT And PDM Methods In The Social And Department Of Kelautan Building Development Project Gresik District.

Badri, S. (1997). Dasar-dasar Network Planning. Jakarta: Pernerbit Rineka Cipta.

DANNYANTI, E. (2016). OPTIMALISASI PELAKSANAAN PROYEK DENGAN METODE PERT DAN CPM (Studi Kasus Twin Tower Building Pasca Sarjana Undip) .

https://wiki.aalto.fi/display/TU22/11.+Project+Management. (n.d.).

Husein, A. (2009). Manajemen Proyek. Yogyakarta: Andi Offset.

Khoiroh, S. M. (2018). Megoptimalkan Crashing Project Pemasangan Saluran Rumah Di Perumahan X Dengan Pendekatan CPM-PERT.

Kurniawan, F. (2020). Analisis Waktu Pelaksanaan Proyek Dengan Menggunakan Metode CPM–PERT Pada Pembangunan Gedung SDN Bibis 113 Surabaya.

Published
2022-03-01
How to Cite
Daffa, M., & Sukanta, S. (2022). Analisis Penerapan Manajemen Waktu Pekerjaan Instalasi Listrik PT. Duta Bangun Sentosa dengan Metode Critical Path Method (CPM) pada Proyek Lampung City. Jurnal Ilmiah Wahana Pendidikan, 8(3), 121-125. https://doi.org/10.5281/zenodo.6301703